Over the last two weeks we have seen a lot of progress on the building, but not a lot of it can be seen. Foundation sealing and water control has been mostly completed and the crews are working on all of the underground plumbing.

This should be the final week of underground work with the steel scheduled to arrive right after the long weekend. By the end of May we will see the basic structure of the building.

Continue to pray for favour, good weather, and safety on the project.