We have completed our framing walkthroughs of both levels, as well as our electrical walkthrough of the second floor (mezzanine). The main floor electrical should be next week. We also have our main water line being installed this week. External boarding has begun with the anticipation of windows in about two weeks. (Click to scroll through pictures or visit Facebook.com/ROVCCalgary for more pictures.)